Week 3, Tuesday

CAD/Hardware

  • Camera fixtures were modified to account for power button and screen
    • used a mill in the workshop in the tech building
  • Model has finished and is ready to be printed
    • Will be using printers in both the tech building and the stem room
  • Proper screws are ordered from McMaster that fit inside the limit switches
    • M2 18-8 Stainless Steel Socket Head Screw

Circuit/Software


  • Motors work, including timeout feature in case of failure of the limit switches
  • Work has begun on making a circuit for the speaker








Cameras

  • Cameras were placed in the box in their proper positions and placed under a heat lamp. Investigation is now going on if they fail or not under these conditions 

Comments

Popular posts from this blog

Camera Field of View Test

Camera Test in the Sun

Week 4, Wednesday