Top Priorities

Thursday, April 6, 2017 Top Priorities: o    Rewire the circuit-board o    Rewrite sound software and make sure all members understand it thoroughly o    Calibrate microphone and speaker o    Set the gain for the microphone o    Check out all software o    Pressure software needs to tap into time and alt. readings o    Integrate New GPS unit and rewrite software as needed to: o    Record GPS altitude o    Time Stamp o    Unmodified Sensor Output o    Perform unit conversion to usable units o    Output format for all sensors: o    GPS altitude, time, raw data, converted data Link for the document: https://drive.google.com/open?id=0B0bMTKNQ-M5-aWRZMThUT3dSeXc

WEEK ELEVEN: August 1, 2016 TETHERED LAUNCH #2 RESULTS

Image
The pressure sensor was not functional prior to launch and we will trouble shoot that component before the next launch. All other components worked properly and had data that made sense. The only exception was at time 12:10 when the payload struck the ground and caused the components to begin writing erroneous data. The erroneous data maintained it's single value for approximately 43 minutes and then all components began giving correct data once again. Please see the graphs for the data that was written from the launch. The GoPro that was facing upward overheated and shut off after 40 minutes of run time due to the fact that it was in direct sunlight for the duration of the test flight. During the main launch the GoPro overheating won't be a problem because it will ascend at a rate which will take it into cooler temperatures within 20 minutes of launch. Spot GPS Data SUCCESS   Accelerometer Data SUCCESS aside from the "Concussion" GPS Data SUCCESS ...

WEEK TEN: July 26, 2016

1. Worked on the netting for the payload. ( Melissa ) 2. Troubleshoot the accelerometer. ( Everyone )

WEEK TEN: July 25, 2016

1. Worked on preparing the netting for the payload. ( Melissa, Sofia ) 2. Shimmed the GoPro cameras. ( Patrick ) 3. Worked on sound experiment. Increased duration of the output. ( Nicholas )

WEEK NINE: July 20, 2016

Image
1. Work on presentation. ( Everyone, mostly Patrick ) 2. Find website that calculates the fill volume, ascent rate, neck lift, and time to burst. The website is here . ( William ) SEE PICTURE 1 PICTURE 1 :   

WEEK NINE: July 19, 2016 - Pre Test Launch

Image
We made several modifications to the test launch for the test launch. We originally wanted the balloon tethered up to about 250 feet. However, the wind could apply enough drag force to break the 100-pound-test tether. To accommodate for this, we tripled the line and sent the balloon to about 75 feet up in the air. We had a lot of fun keeping the balloon from being blown into the ground. The BeagleBone recorded two hours of data while we prepared the payload and the balloon. Of the 30-45 minutes of flight time, the BeagleBone recorded 7-8 minutes of data. Our computer couldn't record data for the rest of the flight because its connection to the power supply loosened and the power supply itself wasn't properly secured. As for the components, they worked as intended except for the accelerometer. The two SpotGPS reported the balloon's location accurately. SEE SPOTGPS DATA . Despite the low flight altitude, the APRS managed to pinpoint its location as well. For some reason, ...

WEEK NINE: July 18, 2016

Image
1. Finished the procedure checklist. ( Sofia, Patrick ) 2. Finished the payload basket. ( Melissa ) SEE PICTURE 1 3. Tested the programs and equipment. ( Nick, Peter ) All the programs but the accelerometer program work as intended. For some reason, only the y-axis of the accelerometer reads a value of about -1.4 g regardless of the orientation.  A hardware connection is the prime suspect. 4. Brainstormed ways to attach the group picture to the bar for the final launch. ( Luis, Melissa, Patrick ) The best idea seems to be attaching the picture to an aluminum sheet and welding the sheet onto the bar. We also measured the ideal distance between the picture and the GoPro, which is 1 foot. 5. Attached picture to the bar for tomorrow's launch. ( Professor Balzarette, Melissa, Patrick ) We temporarily spray-glued the picture onto a sheet of ABS plastic and secured the sheet onto a notch in the bar with industrial strength hot glue. SEE PICTURE 2 We are now prepared for tomorrow...