WEEK NINE: July 18, 2016

1. Finished the procedure checklist. (Sofia, Patrick)

2. Finished the payload basket. (Melissa) SEE PICTURE 1

3. Tested the programs and equipment. (Nick, Peter) All the programs but the accelerometer program work as intended. For some reason, only the y-axis of the accelerometer reads a value of about -1.4 g regardless of the orientation.  A hardware connection is the prime suspect.

4. Brainstormed ways to attach the group picture to the bar for the final launch. (Luis, Melissa, Patrick) The best idea seems to be attaching the picture to an aluminum sheet and welding the sheet onto the bar. We also measured the ideal distance between the picture and the GoPro, which is 1 foot.

5. Attached picture to the bar for tomorrow's launch. (Professor Balzarette, Melissa, Patrick) We temporarily spray-glued the picture onto a sheet of ABS plastic and secured the sheet onto a notch in the bar with industrial strength hot glue. SEE PICTURE 2

We are now prepared for tomorrow's test flight!

NOTE: Find out whether the weight limit includes the tether. If so, we will need to reduce weight because the weight of the tether and the payload exceeds 7 pounds.

Picture 1
Picture 2

EDIT: The ABS plastic sheet is actually adhered with regular hot glue