Week 3, Tuesday

CAD/Hardware

  • Camera fixtures were modified to account for power button and screen
    • used a mill in the workshop in the tech building
  • Model has finished and is ready to be printed
    • Will be using printers in both the tech building and the stem room
  • Proper screws are ordered from McMaster that fit inside the limit switches
    • M2 18-8 Stainless Steel Socket Head Screw

Circuit/Software


  • Motors work, including timeout feature in case of failure of the limit switches
  • Work has begun on making a circuit for the speaker








Cameras

  • Cameras were placed in the box in their proper positions and placed under a heat lamp. Investigation is now going on if they fail or not under these conditions 