WEEK ONE: May 24, 2016
1. Removed old sound experiment from board. (William) SUCCESS
2. Worked on timeline. (Patrick, William) SEE PICTURE 1
3. Removed magnetometer from the circuit. (William) SUCCESS
4. Installed clock into the circuit. Helpful link here.(William) SUCCESS
5. Cleaned up code for accelerometer, added comments and changed the output from printing in a ZYX format to printing in an XYZ format. Accelerometer program finished. (Patrick)
6. Tested Pressure sensor and modified code to write out to a file. (Nick, Peter) SUCCESS
7. Tested clock integration. (Nick, Peter) SUCCESS
8. Figured out how to set date on the beaglebone. NOTE: Has to be in GMT and military. This link helped to determine the process. (Nick, Peter)
9. Worked on code for the internal thermistor and tested functionality. (Peter, Nick) SUCCESS
10. Worked on code for the external thermistor but did not test functionality. (Patrick)
PICTURE 1:
2. Worked on timeline. (Patrick, William) SEE PICTURE 1
3. Removed magnetometer from the circuit. (William) SUCCESS
4. Installed clock into the circuit. Helpful link here.(William) SUCCESS
5. Cleaned up code for accelerometer, added comments and changed the output from printing in a ZYX format to printing in an XYZ format. Accelerometer program finished. (Patrick)
6. Tested Pressure sensor and modified code to write out to a file. (Nick, Peter) SUCCESS
7. Tested clock integration. (Nick, Peter) SUCCESS
8. Figured out how to set date on the beaglebone. NOTE: Has to be in GMT and military. This link helped to determine the process. (Nick, Peter)
9. Worked on code for the internal thermistor and tested functionality. (Peter, Nick) SUCCESS
10. Worked on code for the external thermistor but did not test functionality. (Patrick)