- With the help of the team's advisor (Professor Griffo) a plan was set with a list of goals that need to be accomplished for the success of the project.
- All members in the project were designated specific activities
- 3D Print of Petri Dish (Charles)
- 3D Print of Spot GPS and camera 270-degree (Melissa)
- Circuit Board (Jonny)
- Net for Payload (Grecia)
- Coding (Patrick)
Goals:
- Finish circuit board
- Test Circuit board
- Code Carbon Detector
- Code new GPS on board before installing on board
- 3D Petri Dish / Spot GPS / camera 270-degree
- Code Dish with motor
- Design mounting on board
- Weight payloads (no more than 6 pounds)
- Net for Payload
Today:
- Worked on new circuit board (Jonny)
- Worked on last year's balloon project and cleaned out any 3D prints that were glued to the foam (Melissa, Grecia)
- Cleaned and set up new working area (Melissa, Grecia)